Gas connection work for the Square Bellevue real estate project

The Village of Senneville wishes to inform you that Energir will be carrying out gas connection work on Anciens-Combattants Boulevard starting Monday, June 12, 2023, for approximately 7 days.

The work will be done as part of the Square Bellevue real estate project.

Work details

  • Period of work: From Monday, June 12, for approximately 7 days (approximate end date: Tuesday, June 20).
  • Schedule: Monday to Friday, 9 a.m. to 3 p.m.
  • Location: Anciens-Combattants Boulevard, between Sainte-Anne Street and the entrance of the new clinic.

Obstacles

  • Complete closure of Anciens-Combattants Boulevard southbound, between Sainte-Anne Street and the clinic entrance. A bypass road will be in place for the duration of the work. Please the follow traffic signs.
  • Partial closure of the intersection at the corner of Pacific Avenue and Sainte-Anne Street, with intermittent traffic.
  • To minimize the impact on road users, the work will be carried out outside rush hour, from 9 a.m. to 3 p.m.

Motorists, cyclists and pedestrians are asked to pay particular attention to the signage that will be in place.

Thank you for your cooperation.